Adoption of new grid extension installations

On this page, we explain when it is mandatory for new grid extension installations to be adopted, what steps you must follow to carry out the adoption process, and what costs may apply, in accordance with current regulations.

    When is it necessary for installations to be adopted?

    Regulations stipulate that new grid extension installations:

    1. Executed by a third party via a certified installer, and
    2. Designed to supply more than one consumer, it must be adopted by the distribution company and become part of the local distribution grid.

    they must be transferred to the distribution company and become part of the distribution network in the area.

     

    Stages before the adoption of installations

    The adoption process begins following an access and connection application, wherein the applicant commissions the new grid extension from a certified installer.

     

    Preliminary steps

    phases before managing a transfer
     

     

    1. Access and connection request,
    2. Acceptance of the preliminary proposal,
    3. Access and connection permit, and
    4. Execution of the client's network extension project and assignment management.

     

    Necessary procedures for execution and adoption

    generation steps
     

    Once the preliminary proposal has been accepted, and if the applicant chooses to execute the works for subsequent adoption, the following procedures must be completed:

    • Technical conformity of the design specifications.
    • Documentation review and completion of works.
    • Technical inspection of the works (supervision).
    • Signing of the adoption agreement and legalisation or change of ownership, if applicable.
    • Commissioning of the installations.

Guide for the transfer of installations

Transfer of installations

Guide for the management

Here you will find all the relevant information for the transfer of new grid extension installations.

Frequently asked questions